VALUE:
£365,000.00
TIMESCALE:
7-weeks
“Our project at Cavendish School successfully transformed the roof and interior spaces, ensuring a safe, well-insulated, and vibrant environment for students and staff, all completed smoothly over the summer break”
Client
Cavendish Education Trust
Value
£365,000.00
7-weeks
Type of Contract
JCT Intermediate Building
Contract 2016 Edition.
Consultant
Bailey Garner
Scope of Works
The proposed works are the replacement of the schools main pitched roof covering, including the provision of new insulation, battens, flashings, roofline goods and associated roofing components. The pitched roof will be renewed with a Marley System. The replacement of insulation shall conform to Part L of the Building Regulations, and ventilation shall conform to BS 5250.
Challenges
- The challenge was to complete this project originally planned for two summer holidays within a single 6-week summer period.
- Another Challenge was to create a new weathervane that faithfully replicated the original design while incorporating a modern twist.
Solutions
- We achieved this by pre planning of material ordering and erecting the scaffolding out of hours before the summer term ended. We added additional labour to the project and hired and telehandler to speed to the distribution of materials to roof level. We also added additional loading bays throughout the scaffold so all materials were loaded into the correct roof section, aaain savina on labour.
- We engaged a traditional blacksmith to attend and remove to original weathervane, restore it back to its original glory, whilst adding a personalise touch with the schools original build date 1939 engraved within the new flag. To ensure this didn't hold up the main roof, the weathervane was reinstated via MEWP, so the project was held up at any stage.
Key Highlights
- This project was a testament to the "can-do" attitude of APC. With our team working late daily and staying locally to the school, we committed to a difficult task but one that we were confident we could achieve, and ultimately delivered.
You may also like
VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved
VALUE: £925,000 TIMESCALE: 40-weeks “The project involved the careful restoration and
VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary