Home Goose Green School SE22 8HG
Goose Green School SE22 8HG
VALUE:
£925,000
TIMESCALE:
40-weeks
“The project involved the careful restoration and replacement of heritage timber windows at Goose Green School, blending meticulous craftsmanship with efficient planning to enhance the school’s historic charm with minimal disruption.”
Client
Value
Type of Contract
Consultant
Scope of Works
The scope of work included site setup, scaffolding replacement of single glazed timber heritage windows to the front of the building and spliced repairs and overall works followed by redecorating the flank and rear elevation windows.
Challenges
- Completing a significant amount of work within an occupied school, involving planning works to critical areas such as circulation spaces, so that the work takes place during holidays and weekends – this was to limit disruption in high traffic areas.
- Dealing with the control of dust in an existing school environment, using additional extraction and dust control plant and equipment.
- Selecting the correct sub- contractor from our approved list to ensure they had the correct resource who are fully trained in their craft and Enhanced DBS checked.
Solutions
- We have extensive experience of working in live school sites so our site managers are well versed when it comes to how to manage sub- contractors and suppliers in these environments – making sure everyone is aware of the brief.
- We had agreed a sequence of works with the school that meant that we only ever take two classrooms at any one time (and they had an overspill area that could be used for the two classrooms which were taken out of actions) and by doing this we were able carefully complete the works to plan as we moved around the building whilst ensuring that all rooms were adequately sealed with appropriate dust extraction machines in place.
Why This Case Study
- This project has been selected as it was a fast turnaround project in an occupied school.
- This project has been elected as it involved timbe window replacement works which are like for like with Rhyl School.
- This project has been selected as this project involved a significant amount of timber restoration to existing windows as well as the replacement works noted above using the same system of repairs and decorations that has been specified at Rhyl School.
You may also like
VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved
VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary
VALUE: £35,082.75 TIMESCALE: 2-weeks “At Belvedere Infant School, we completed a