Home Hailsham Community College
Hailsham Community College
VALUE:
£230,000
TIMESCALE:
6-weeks
“This project delivers a comprehensive electrical upgrade for Hailsham Community College, ensuring safety, efficiency, and a seamless installation experience tailored to the school’s unique needs.”
Client
Hailsham Community College
Value
£230,000
Duration
6-weeks
Type of Contract
JCT Design & Build
Consultant
East Sussex
Scope of Works
Full distribution upgrade including mains intake, switch gear, isolators and sub distribution boards. Emergency lighting install including design.
Challenges
- All works to be carried out within school holidays, evenings and weekends.
- All circuits (small power, lighting and emergency lighting had to be fully tested and energised before the start of every school day.
- Very old existing installation with no relevant paperwork so all circuits had to be individually investigated.
- Minimal existing emergency lighting was in place.
Solutions
- Pre planning all works making sure full design was approved and the relevant materials ordered and on site and ready to install.
- Employed an electrical designer to carry out the emergency lighting design understanding the schools Fire and Exit strategies.
- Contracted electrician working planned out of hours to ensure deadlines met.
Why This Case Study
- Successful project with many challenges to overcome whilst being conscientious of the school's needs.
- Our works took place sitewide with emergency lighting installed within every building where required including sports hall and external works.
- Distribution boards were also upgraded site wide including the main intake, we left the school happy with a very user-friendly installation, including all relevant certificates, paperwork and as built drawings.
You may also like
VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved
VALUE: £925,000 TIMESCALE: 40-weeks “The project involved the careful restoration and
VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary