Home Darrick Wood School BR6 8ER
Darrick Wood School BR6 8ER
VALUE:
£295,000
TIMESCALE:
6-weeks
“The project at Darrick Wood School delivered a comprehensive electrical upgrade, enhancing safety and efficiency while minimizing disruption to the school’s daily operations.”
Client
Value
£295,000
6-weeks
Type of Contract
JCT Design & Build
Consultant
Bromley Council
Scope of Works
The scope of the work was to design, supply and install Classroom upgrades, electrical works for AC install, full EICR and validations including remedial works to bring the current electrics up to current regulations.
Challenges
- All works to be carried out within school holidays. All works scheduled very specifically with materials pre ordered to ensure hold ups on site.
- Design and build project so had to carry out the full design meeting the clients requirements.
- EICR's had to all be done out of hours as unable to isolate and test circuits within a live school.
- Asbestos within Distribution Board.
Solutions
- Designs had to be carried out before the works started in order for us to procure the correct materials and plant making sure we could fulfil the project within the allocated time.
- Speaking to NICEIC on regular occasions to make sure we carry out the relevant remedial works to keep within budget but also handover a satisfactory installation.
- planned asbestos removal.
Why This Case Study
- We have selected this project for our case study as works took place in over 70% of the school building many of different ages with different types of existing installation methods.
- All targets hit within the allocated times and budget, the school were happy with the outcome.
You may also like
VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved
VALUE: £925,000 TIMESCALE: 40-weeks “The project involved the careful restoration and
VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary