Cavendish School
VALUE:
£370,000
TIMESCALE:
6-weeks
“This project brought new life to Cavendish School’s main roof, delivering a beautifully renewed structure with modern insulation and a restored, customized weathervane.”
Client
Cavendish School
Value
£370,000
Duration
6-weeks
Type of Contract
JCT Design & Build
Consultant
Bailey Garner
Scope of Works
Pitched Roof Replacement Project (Large Humanities Block). The works comprise of the re-covering of various pitched & flat roofs to the school which also included associated M&E work and builders works. Internal works carried out to classroom and hallway with ceiling and lighting. This includes loft insulation to all areas of pitched roofing.
Challenges
- There was a delay in obtaining the results of the asbestos survey. When they were received asbestos was identified in roof void, foam needed to be removed for fire regulations which then had to be dealt with by the Asbestos contractor.
- The was a short lead-in time to complete designs.
- There was insufficient time to fabricate the doors based on 8-week fabrication period which meant that we need to find alternative suppliers.
Solutions
- The asbestos issue was over come by working in the areas that were asbestos clear and then working on the other areas once the asbestos had been removed and deemed safe to work. By adopting this approach, the works were completed on time.
- Ensuring that we had a detailed programme and procurement schedule.
- Using our extensive approved supply chain, we found alternative suppliers with shorter lead times.
Why This Case Study
- Successful project with many challenges to overcome whilst being conscientious of the school's needs.
- Because this is a very similar project involving the insulation of new fire doors, fire glass and fire stopping - all being completed within a short timeframe over the summer holidays.
- Because the same subcontractors / suppliers completed this project for us as the ones we intend on using for the Greenwich 5 sites.
You may also like
VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved
VALUE: £925,000 TIMESCALE: 40-weeks “The project involved the careful restoration and
VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary