Beckmead Moundwood Academy
VALUE:
£625,000
TIMESCALE:
6-weeks
“At Beckmead Moundwood Academy, we delivered a smooth, timely roof, window, and door refurbishment, ensuring minimal disruption to students with careful planning and round-the-clock commitment.”
Client
Beckmead Moundwood
Acedemy
Value
£625,000
Duration
6-weeks
Type of Contract
JCT Standard Building Contract
Consultant
Bailey Garner
Scope of Works
The scope of work included site setup, scaffolding External Refurbishment Works – Roof Replacement, Window & Door Replacement.
Challenges
- We were awarded the contract late in the season, therefore work had to be done during termtime. Safeguarding was imperative as some of the work had to be carried out while students were in attendance. The weather also had to be always kept in mind.
- Compromises had to be made to make sure the students/staff were safe and happy. This was done by out-of-hours works and weekend works for all the works unable to be completed when school was open..
- Selecting the correct sub- contractor from our approved list to ensure they had the correct resource who are fully trained in their craft and Enhanced DBS checked.
Solutions
- We have extensive experience of working in live school sites so our site managers are well versed when it comes to how to manage sub- contractors and suppliers in these environments – making sure everyone is aware of the brief.
- A key priority for us was to make sure that we didn’t disrupt the daily activities of the school and pupils. We did this through regular communication with the school’s estate team making sure they knew what work we were carrying out, when and where we would be carrying it out and advising them of any areas that would not be available. We also worked closely with the school regarding access, egress, logistics and parking.
Why This Case Study
- This project has been selected as it has all four elements that New End Primary school requires (roofing, doors, windows and external refurb).
- This project has been elected as it involves being completed over the summer holidays. This project has been selected due to the lessons that were learnt at Beckmead Moundwood Academy.
- Lead times need to be assessed weekly and all stakeholders advised.
- Housekeeping in a live environment needs to be impeccable at all times.
- Communication between all stakeholders needs to be done on a daily basis.
You may also like
VALUE: £450,000 TIMESCALE: 6-weeks “The project at Bromley Primary School involved
VALUE: £925,000 TIMESCALE: 40-weeks “The project involved the careful restoration and
VALUE: £36,082.75 TIMESCALE: 4-weeks “A delightful renovation project at Dulverton Primary